WORKING EXPERIENCE               

KEJURUTERAAN QKS SDN. BHD 

Duration Position                 :                1st June 2001 until at present

 Position                              :                Project Manager

 Main Task                           :               Tendering, Proposal, Costing, Evaluating, Planning, Scheduling,

Monitoring, Controlling, Coordination, Prepare and Evaluate Job Safety Analysis and monitoring, project reporting and claiming, technical advisor, liase with client, subcontractor, consultant, local authority (e.g DOSH, BOMBA) or other parties who may involve especially in term of technical, quality, safety, commercial and contractual matter.

  Project Involve

1.        The Construction, Testing and Commissioning of Semi-Fixed Full Fire Protecting System for PSR-2 Crude Oil Tank.

Client                                   :                Petronas Penapisan (Melaka) Sdn. Bhd.

Contract Amount                 :                Rm 3 millions

Duration                              :                September 2001 - April 2002.

 Work Descriptions                :

 ·         Liaise with DOSH and BOMBA on any regulatory requirement.

·         Fabrication and installation 49 lines of piping including supports etc with 29,000 total dia-inch and 67Ton Pipe support.

·         Fabrication and installation of 643 nos pipe support foundation.

·         Fabrication and installation 7 nos of firewall.

·         Installation 49 sets of Pourer.

·         Testing and commissioning of 49 new fire protecting system.

  1. The Removal And Installation Of High Pressure Flash Drum At Gas

Processing Plant Complex B (GPP-B) – Mini Shut Down

Client                                  :                Petronas Gas Berhad.

Contract Amount                 :                Rm 2 millions

Duration                              :                January 2002 – February 2002

 

Work Descriptions                :

 

·         Removal of internal and external vessel attachment as such piping, electrical parts, Internal tray   and rings, insulation and etc.

·         Removal the existing pressure vessel and re-install the new pressure vessel.

·         Heavy lifting work including lifting pressure vessel cross the existing life pipeline.

·         Re-install all the internal and external attachment as such piping, electrical parts, internal tray and rings, fireproofing, insulation and etc.

 

  1. Pressure Vessel Overhaul Work – Shut Down Work.

 

Client                                      :               MTBE Malaysia Sdn. Bhd.

 Contract Amount                   :              Rm 1 million

 Duration                                 :            July 2002 – Sept 2002                                        

 Work Description: 

·         Preparing and monitoring overall schedule.

·         Attending daily progress meeting with client.

·         Preparing and submitting all related reports and documents.

·         Opening and cleaning 102 nos of unfired Pressure Vessel.

·         Repairing any defect finding.

·         Replacing some existing vessel with new vessel.

  1. The Engineering, Procurement, Construction And Commissioning Of A New Product Delivery Center At Miri, Sarawak

 

Client                                    :               Petronas Dagangan Sdn. Bhd.

 Contract Amount                 :                Rm 2.5 Millions

 Duration                               :                July 2002 – December 2002

Work Description:

·         Engineering work and obtain all regulatory approval.

·         Fabrication and installation 20 nos Skid Tank with 20000GL capacity per tank.

·         Fabrication and installation of receiving and delivery pipe lines including pipe supports.

·         Installation 2 units of bunkering and delivery pumps.

·         Installation 2 units PD Meter (Electronic Type) and 1 unit PD Meter (Mechanical type).

·         Installation 2 units of Loading Arm.

·         Installation 1 unit of Diesel Dispenser.

·         Installation 1 unit of septic tank.

·         Electrical work for overall plant.

·         Fabrication and installation of steel structure for Skid Tank and Tank Truck Loading.

·         Construction of civil foundation for tanks, pumps, Tank Truck Loading, Pipe support, Dispenser and etc.

·         Painting and marking works.

·         Testing and commissioning.

 

Tender/Proposal Involve

 1.             The Engineering, Procurement, Construction and Installation of Platforms for maintenance

purpose.

Client :                Petronas Fertilizer (Kedah) Sdn. Bhd.

 2.             Electrical Works for Maintenance Minor Civil Building-Start-up Heater Transformer.

Client :                Petronas Fertilizer (Kedah) Sdn. Bhd.

 3.             Year 2002 Turnaround Associated Works At Gas processing Plant-1 (GPP 1 Kertih Terengganu)

Client :                Petronas Gas Berhad.

4.                Installation Of New Upright Sprinkler System For Warehouse Building Year 2002.

Client :                MTBE Polypropylene Malaysia Sdn. Bhd.

 5.             Pressure Vessel Overhaul Work – Shut Down Work Year 2002.

Client :                MTBE  Malaysia Sdn. Bhd.

 6.             Heat Exchanger & Air Fin Cooler Overhaul Work–Shut Down Work Year 2002.

Client :                MTBE Malaysia Sdn. Bhd.

 7.             Package II – Work Site Clearing And Preparation Work PFK Fertilizer Project Year 2002.

Client :                AMEC (Malaysia) Sdn. Bhd.             

8.                Turnaround Associated Works At Gas Processing Plant-4 (GPP 4 Kertih Terenggannu) Year 2002

Client :                Petronas Gas Berhad.

  9.             Term Contract For The Provision Of General Mechanical Services Year 2003.

Client :                Petronas Penapisan (Melaka) Sdn. Bhd.

  10.           The Maintenance Works, PPMSB PSR-2 Year 2003 Turnaround

Client :                Petronas Penapisan (Melaka) Sdn. Bhd.

11.                 Mechanical, Rotating And Associated Turnaround Works For Year 2003.

Client :                Petlin Malaysia Sdn. Bhd. Kertih Terengganu.

 12.                 Mechanical & Associated Works POD Plant Turnaround of Export Terminal Unit 1&2 Year 2003.

Client :                Petronas Gas Malaysia Berhad.

13.           The Construction Of PSR-2 Turnaround Facility.

Client :                Petronas Penapisan Melaka Sdn. Bhd.

 14.           Module 2/3 Boilers And Utility Area Work For MLNG Rejuvenation And MLNG Dua                                            Revamp(MRR 250 Project)

Client :                Malaysia LNG Sdn. Bhd.

15.           Module 2/3 Mechanical Work For MLNG Revamp & Rejuvenation (MRR 185)

Client :                Malaysia LNG Sdn. Bhd.

 16.           The Replacement Of Pipeline At Phase 2 Area And Ancillary Works

Client :                Johor Port Berhad

 17.           Heat Exchanger Equipment DOSH 2004-2006 Turnaround Works

Client :                Malaysia LNG Sdn. Bhd.

 18.           Pressure Vessel, Heat Exchanger And Associated Work For PDH Turnaround Work.

Client :                MTBE Malaysia Sdn. Bhd.

 19.           Remove, Install And Supply Secondary Seal For Tank T-7309.

Client :                Petronas Penapisan Melaka Sdn. Bhd.

 20.           Boiler Superheater Tube Replacement.

Client :                Asean Bintulu Fertilizer Sdn. Bhd.

 21.                Provision Of Utility Facility For Tank T-7104 Cleaning Work

Client :                Petronas Penapisan Melaka Sdn. Bhd. 

22.           The Piping Fabrication & Mechanical Equipment Installation Works For Kizomba-B Drilling Rig

Client :                Malaysia Shipyard And Engineering Sdn. Bhd.

 23.           MP-LP Steam Tie-in At Crude Storage Areas (Hot Tapping Work).

Client :                Petronas Penapisan Melaka Sdn. Bhd.

 24.           New Independent Oil Terminal Project

Client :                ASSAR Chemical Sdn. Bhd.

25.           Leak Rectification at GPP Complex A & B, CUF Kertih,Kemaman & Gabeng.

Client :                Petronas Gas Berhad.

 

TELLUS ENGINEERING CONSTRUCTION PTE. LTD. /NEXUS SEALAND ENGINEERING SDN. BHD.

 Duration Position                 :                17th June 2000 – 31st May 2001

 Position                                 :                Site Manager / Project Manager

 Project Involved                   :                A/G Piping Works (HEATER AREA) Malaysia Olefins Project for

Petronas/UCC Joint Venture at Kertih Terengganu.

 Contract Amount                 :                Rm 3 million

 

Client                                      :                 Sukwon Idche Engineering (M) Sdn. Bhd.

Main Task                             :               Planning, Scheduling, Costing, Evaluating, Coordination and

Monitoring on going project, project reporting, claiming as well as technical advisor, liase with sub-contractor on claiming and contractual matter.

 Details Task                          :  To assist site manager on monitoring the site erection on planning,

Scheduling, Reporting, Technical Solution, Implementation on Safety

Regulation as per DOSH requirements, Cost controlling, Coordination

with main contractor as well as supervisor on site. Day to day interface

with in charge person on site, Prepare the monthly progress claim to

main contractor, Drawing controlling, estimating the new incoming

work area and finally advising Site Manager on any effective tactical

decision making on costing and planning site activities.

PROMTO-SIKOJAYA SDN. BHD.

 Duration Position                 :                31st Jan 2000-15th June 2000

 Position                                 :                Project Manager (Planning Section)

 Main Task                             :                Planning, Scheduling, Evaluating of tendering projects in execution.

                                                                Monitoring the project progress against planned schedule.

 Details Task                          :               To breakdown the project into distinct activities which includes the

time estimation for the activities and sequence of the works.

Establish project schedules and monitor against productivity.

Feedback the updates schedule to Project Manager and management.

To formulise an effective tactical decision making based on strategy.

Establish resources list of manpower, equipment, tools and

consumables.

Establish manpower, equipment loading based on the tender schedule.

To establish and evaluation of project in term of resources, i.e

manpower, tools, consumables and etc.

 Responsibility                      :                To co-ordinate in logical order all the activities, person, machines and

                                                                Materials necessary to complete a project.

Prepare, updating project schedule on daily, weekly and monthly report.

Confirmation with other parties that may have involvement on

                                                                tendering process.

 Project Tendering &

Negotiation Involved                 :              

              1.       The 3 X 700 MW Coal Fired Power Station Project Manjung Perak for TNB Janamanjung Sdn. Bhd

              2.       TNB Gelugor Pulau Pinang Power Station Upgrading Project.

              3.       Sepang Power Station – Simmens Open Cycle Stage

 Involved on direct high level negotiation with sub-contractor and ABB Power Generation Sdn. Bhd. on

final claiming matter for the Titan Petrochemical projects as part of close up project procedure.

PROMTO-SIKOJAYA SDN. BHD.

  Duration Position                 :                1st Jan 1999 until 31st Jan 2000

 Position                                 :                Acting Site Manager

 Project    Involved                                :                 Titan Petrochemical Combined Cycle Power Plant

 Client                                      :                ABB Power Generation Sdn. Bhd. (Now As Alstom Power

Malaysia Sdn. Bhd.)

 Contract Amount                 :                Rm 6 million

 Installation and pre-commissioning of ABB Combined Cycle Power Plant for Titan Petrochemical plant at Tanjung Langsat, Johor Bahru. 

a)       1 unit ABB (GT-21) Gas Turbine including all its associated auxiliary equipment, piping, electrical & instrumentation.

b)       1 unit ABB Heat Recovery System Generation (HRSG) including structural erection, auxiliary equipment, piping, electrical & instrumentation.

c)       1 unit ABB MP Steam Turbine including all its auxiliary equipment, piping, electrical & instrument system.

 Mechanical and Structural Installation & Pre-commissioning: -

 Ø       Boiler Modules (Superheater, Evaporator and Economiser)

Ø       Boiler Feed Pumps

Ø       Boiler Circulation Pumps

Ø       Gas Turbine

Ø       Auxiliary equipment & piping systems, valves and fittings

 Electrical & Instrument Installation and Pre-commissioning: -

Ø       Transformers

Ø       Main Switch Board / Switchgears

Ø       Electrical Feeders

Ø       Electrical Distribution Panels

Ø       Instrumentation Control Panels

Ø       Instrumentation Field Instrument

Ø       E & I Auxiliary accessories such as cable trays/ladders, power cables, instrument cables, support, etc.

 Duties and responsibilities: -

 Ø       Ensure every required resource such as tools, equipment, project materials; technical drawings, other relevant referential documents, external technical supports and general site administrative support are in place and being closely monitored.

 Ø       Ensure the plant is constructed in accordance with client and main contractor requirements.

 Ø       Site management and co-ordination with sub-contractor.

 Ø       Management and co-ordination of resources to ensure the programme of work is achieved.

 Ø       Adherence to the Safety Policy and requirements per Occupational Health and Safety Management Plan.

 Ø       Employee relation plan.

 Ø       Quality requirements for site works.

 Ø       Identify and record any non-conformity relating to the job.

 Ø       Represent company in day-to-day interfaces with client, main contractor and sub-contractor on reporting.

Ø       Advising Project Manager or Procurement Manager of shortfalls in supply of plant or equipment to site.

 Ø       Authorise to purchase material from site.

Ø       Authorise sub-contractor to precede work on variation order.

Ø       Authorise to control further processing or installation of non-confirming product until the deficiency or unsatisfactory condition has been corrected.

 Ø       Controlling project budget.

  

PROMTO-SIKOJAYA SDN. BHD.

Duration Position                 :                22nd June 1998 until 31st December 1998

 Position                                 :                Site Engineer

 Project    Involved                                :                Titan Petrochemical Cogen 2 X 40MW Power Plant

 Client                                      :                ABB Power Generation Sdn. Bhd. (Now As Alstom Power

Malaysia Sdn. Bhd.)

 Contract Amount                 :                Rm 4 million

 Installation and pre-commissioning of ABB Co-Gen Power Plant for Titan Petrochemical Sdn. Bhd at Pasir Gudang Johor.

a)       2 units ABB GT-10 Gas Turbine including all its associated auxiliary equipment, piping systems and electrical cabling works.

b)       2 units of ABB Heat Recovery System Generation (HRSG) including structural erection, auxiliary equipment, piping, electrical & instrument systems.

Mechanical and Structural Installation & Pre-commissioning: -

Ø       Boiler Modules ( Superheater, Evaporator and Economiser )

Ø       Boiler Feed Pumps

Ø       Boiler Circulation Pumps

Ø       Gas Turbine

Ø       Auxiliary equipment & piping systems, valves and fittings

Electrical & Instrument Installation and Pre-commissioning: -

Ø       Transformers

Ø       Main Switch Board / Switchgears

Ø       Electrical Feeders

Ø       Electrical Distribution Panels

Ø       Instrumentation Control Panels

Ø       Instrumentation Field Instrument

Ø       E & I Auxiliary accessories such as cable trays/ladders, power cables, instrument cables, support, etc.

 

EQUATOR ENGINEERING SDN. BHD.

 Duration of Employment                          :                Sept 1996 - June 1998

 Position                                                 :                Mechanical Engineer

 Project    Involved                                                :                TNB SSAA Power Station Phase III 2 X 500MW Turbine Contract. 

Client                                                      :                TBV Power (M) Sdn. Bhd.

 Contract Amount                                 :                Rm 45 million

 Installation and pre-commissioning of GE 2 X 500MW Power Station for TNB at Kapar Klang Selangor. 

a)       2 units of GE Steam Turbine including all its associated auxiliary equipment, piping systems. 

b)       Mechanical equipment for Electrochloronation Plant. 

c)       Piping for balance of plants systems.

d)       2 units of Condenser. 

e)       Mechanical equipment for Balance of plants systems. 

f)        Mechanical equipment for CW Pump house. 

g)       Mechanical equipment and piping for Demin Plant. 

Duties & responsibilities: -

 Ø       In-charge in preparing, updating project timetable on daily, weekly and monthly progress report.

Ø       Updating actual activities which to be compared with planned activities using Primavera Project Planner.

Ø       Monitoring and supervising mechanical erection, piping and welding activities.

Ø       All project technical and administrative documentation are properly filed to ensure smooth closing up upon project completion.

Ø       Ensure all safety procedures are complied in all critical works execution such as heavy lifting, scaffolding, confined space entry and so on.

Ø       Issue purchase order to purchase material from site.

Ø       Co-ordinate with other parties that may have some involvement on the project.

Ø       Supervising one piping section consist of 12 semi skilled pipe fitters, 12 skilled pipe fitters and one foreman.

 

CMKS(M) SDN. BHD.

 Duration of Employment                          :                July 1993 until Sept 1994

 Position                                                 :                Technician

 Duties & responsibilities:

 Ø       Maintenance of mould punching and drilling machines.

Ø       Modification of mould as per new design.

Ø       Repairing mould in order to support production line.

Ø       Operates of various machinery’s as milling, grinding and wire cut.

Ø       Incharge of incoming & outgoing goods.

Ø       Supervise 10 operators.

 

REFEREES

 1.        Prof. J. Rhodes (Project Supervisor)

Department of Mechanical Engineering

University of Strathclyde Glasgow U.K

2.        Madam Rokiah Mohamad Noor (Assistance Manager)

CMKS (M) Sdn. Bhd.

Pasir Gudang Industrial Estate

Johor.

3.        Osman Bin Asri (Assistance Manager)

EQUATOR Engineering Sdn. Bhd.

Shah Alam Selangor.

4.        Lim Yew Hock (Assistant Purchasing Officer)

Promto-Sikojaya Sdn. Bhd.

Lot 10, Jalan U1/15, Seksyen U1

Hicom Glenmarie Industrial Park.

40150 Shah Alam Selangor.  

5.        Malik Bin Sulaiman (PMSI)

ALSTOM POWER Sdn. Bhd. (Company No. 243308H)

21st Floor, Wisma Genting,

28, Jalan Sultan Ismail,

50250 Kuala Lumpur.

6.        Keneeth Ngui (PMSI)

ALSTOM POWER Sdn. Bhd. (Company No. 243308H)

21st Floor, Wisma Genting,

28, Jalan Sultan Ismail,

50250 Kuala Lumpur.

7.        Riduan Bin Buyong

AMEC (Malaysia) Sdn. Bhd.

37th Floor Menara PNB

201A Jalan Tun Razak,

50450 Kuala Lumpur.

8.        Daniel Wong Bin Abdullah

Petronas Penapisan Melaka Sdn. Bhd.

Persiaran Penapisan

76300 Sungai Udang

Melaka.

9.        Mohd. Bakhit Bin Mohd. Nor

Petronas Gas Berhad.

KM 8, Kg Tok Arun Off Jalan Santong,

23100 Paka, Dungun,

Terengganu.

10.     Zubir Bin Abdul Razak

Petronas Dagangan Berhad

Level 33, Tower 1, Petronas Twin Towers,

Kuala Lumpur City Centre,

50088 Kuala Lumpur.