Duration
Position
:
1st June 2001 until at present
Position
:
Project Manager
Main
Task
:
Tendering, Proposal, Costing, Evaluating, Planning, Scheduling,
Monitoring, Controlling, Coordination, Prepare and Evaluate Job Safety Analysis and monitoring, project reporting and claiming, technical advisor, liase with client, subcontractor, consultant, local authority (e.g DOSH, BOMBA) or other parties who may involve especially in term of technical, quality, safety, commercial and contractual matter.
Project
Involve
1.
The Construction, Testing and Commissioning of Semi-Fixed Full Fire
Protecting System for PSR-2 Crude Oil Tank.
Client : Petronas Penapisan (Melaka) Sdn. Bhd.
Contract Amount : Rm 3 millions
Duration : September 2001 - April 2002.
Work Descriptions :
·
Liaise with DOSH
and BOMBA on any regulatory requirement.
· Fabrication and installation 49 lines of piping including supports etc with 29,000 total dia-inch and 67Ton Pipe support.
·
Fabrication and installation of 643 nos pipe support foundation.
·
Fabrication and installation 7 nos of firewall.
·
Installation 49 sets of Pourer.
· Testing and commissioning of 49 new fire protecting system.
The Removal And Installation Of High Pressure Flash Drum At Gas
Processing
Plant Complex B (GPP-B) – Mini Shut Down
Client : Petronas Gas Berhad.
Contract Amount : Rm 2 millions
Duration : January 2002 – February 2002
Work Descriptions :
· Removal of internal and external vessel attachment as such piping, electrical parts, Internal tray and rings, insulation and etc.
· Removal the existing pressure vessel and re-install the new pressure vessel.
· Heavy lifting work including lifting pressure vessel cross the existing life pipeline.
· Re-install all the internal and external attachment as such piping, electrical parts, internal tray and rings, fireproofing, insulation and etc.
Pressure Vessel Overhaul Work – Shut Down Work.
Client
:
MTBE Malaysia Sdn. Bhd.
Contract Amount : Rm 1 million
Duration : July 2002 – Sept 2002
Work
Description:
· Preparing and monitoring overall schedule.
· Attending daily progress meeting with client.
· Preparing and submitting all related reports and documents.
· Opening and cleaning 102 nos of unfired Pressure Vessel.
· Repairing any defect finding.
· Replacing some existing vessel with new vessel.
The Engineering, Procurement, Construction And Commissioning Of A New Product Delivery Center At Miri, Sarawak
Client : Petronas Dagangan Sdn. Bhd.
Contract Amount : Rm 2.5 Millions
Duration : July 2002 – December 2002
Work
Description:
· Engineering work and obtain all regulatory approval.
· Fabrication and installation 20 nos Skid Tank with 20000GL capacity per tank.
· Fabrication and installation of receiving and delivery pipe lines including pipe supports.
· Installation 2 units of bunkering and delivery pumps.
· Installation 2 units PD Meter (Electronic Type) and 1 unit PD Meter (Mechanical type).
· Installation 2 units of Loading Arm.
· Installation 1 unit of Diesel Dispenser.
· Installation 1 unit of septic tank.
· Electrical work for overall plant.
· Fabrication and installation of steel structure for Skid Tank and Tank Truck Loading.
· Construction of civil foundation for tanks, pumps, Tank Truck Loading, Pipe support, Dispenser and etc.
· Painting and marking works.
· Testing and commissioning.
Tender/Proposal Involve
1. The Engineering, Procurement, Construction and Installation of Platforms for maintenance
purpose.
Client
:
Petronas Fertilizer (Kedah) Sdn. Bhd.
2. Electrical Works for Maintenance Minor Civil Building-Start-up Heater Transformer.
Client
:
Petronas Fertilizer (Kedah) Sdn. Bhd.
3. Year 2002 Turnaround Associated Works At Gas processing Plant-1 (GPP 1 Kertih Terengganu)
Client
:
Petronas Gas Berhad.
4. Installation Of New Upright Sprinkler System For Warehouse Building Year 2002.
Client :
MTBE Polypropylene Malaysia Sdn. Bhd.
5. Pressure Vessel Overhaul Work – Shut Down Work Year 2002.
Client : MTBE Malaysia Sdn. Bhd.
6. Heat Exchanger & Air Fin Cooler Overhaul Work–Shut Down Work Year 2002.
Client
:
MTBE Malaysia Sdn. Bhd.
7. Package II – Work Site Clearing And Preparation Work PFK Fertilizer Project Year 2002.
Client
:
AMEC (Malaysia) Sdn. Bhd.
Client :
Petronas Gas Berhad.
9.
Term Contract For The Provision Of General Mechanical Services Year 2003.
Client :
Petronas Penapisan (Melaka) Sdn. Bhd.
10.
The Maintenance Works, PPMSB PSR-2 Year 2003 Turnaround
Client :
Petronas Penapisan (Melaka) Sdn. Bhd.
11.
Mechanical, Rotating And Associated Turnaround Works For Year 2003.
Client :
Petlin Malaysia Sdn. Bhd. Kertih Terengganu.
12.
Mechanical & Associated Works POD Plant Turnaround of Export Terminal
Unit 1&2 Year 2003.
Client :
Petronas Gas Malaysia Berhad.
13.
The Construction Of PSR-2 Turnaround Facility.
Client :
Petronas Penapisan Melaka Sdn. Bhd.
14.
Module 2/3 Boilers And Utility Area Work For MLNG Rejuvenation And MLNG
Dua
Revamp(MRR 250 Project)
Client
:
Malaysia LNG
Sdn. Bhd.
15.
Module 2/3 Mechanical Work For MLNG Revamp & Rejuvenation (MRR 185)
Client
:
Malaysia LNG Sdn. Bhd.
16.
The Replacement Of Pipeline At Phase 2 Area And Ancillary Works
Client
:
Johor Port Berhad
17.
Heat Exchanger Equipment DOSH 2004-2006 Turnaround Works
Client
:
Malaysia LNG Sdn. Bhd.
18.
Pressure Vessel, Heat Exchanger And Associated Work For PDH Turnaround
Work.
Client
:
MTBE Malaysia Sdn. Bhd.
19.
Remove, Install And Supply Secondary Seal For Tank T-7309.
Client
:
Petronas Penapisan Melaka Sdn. Bhd.
20.
Boiler Superheater Tube Replacement.
Client
:
Asean Bintulu Fertilizer Sdn. Bhd.
21.
Provision Of Utility Facility For Tank T-7104 Cleaning Work
Client
:
Petronas Penapisan Melaka Sdn. Bhd.
22.
The Piping Fabrication & Mechanical Equipment Installation Works For
Kizomba-B Drilling Rig
Client
:
Malaysia
Shipyard And Engineering Sdn. Bhd.
23.
MP-LP Steam Tie-in At Crude Storage Areas (Hot Tapping Work).
Client
:
Petronas Penapisan Melaka Sdn. Bhd.
24.
New Independent Oil Terminal Project
Client
:
ASSAR Chemical Sdn. Bhd.
25.
Leak Rectification at GPP Complex A & B, CUF Kertih,Kemaman &
Gabeng.
Client
:
Petronas Gas Berhad.
TELLUS
ENGINEERING CONSTRUCTION PTE. LTD. /NEXUS SEALAND ENGINEERING SDN. BHD.
Duration
Position
:
17th June 2000 – 31st May 2001
Position
:
Site Manager / Project Manager
Project
Involved
:
A/G Piping Works (HEATER AREA) Malaysia Olefins Project for
Petronas/UCC
Joint Venture at Kertih Terengganu.
Contract
Amount
:
Rm 3 million
Client
:
Sukwon Idche Engineering (M) Sdn. Bhd.
Main
Task
:
Planning, Scheduling, Costing, Evaluating, Coordination and
Monitoring on going project, project reporting, claiming as well as technical advisor, liase with sub-contractor on claiming and contractual matter.
Details
Task
: To assist site manager on
monitoring the site erection on planning,
Scheduling,
Reporting, Technical Solution, Implementation on Safety
Regulation
as per DOSH requirements, Cost controlling, Coordination
with
main contractor as well as supervisor on site. Day to day interface
with
in charge person on site, Prepare the monthly progress claim to
main
contractor, Drawing controlling, estimating the new incoming
work
area and finally advising Site Manager on any effective tactical
decision
making on costing and planning site activities.
PROMTO-SIKOJAYA
SDN. BHD.
Duration
Position
:
31st Jan 2000-15th June 2000
Position
:
Project Manager (Planning Section)
Main
Task
:
Planning, Scheduling, Evaluating of tendering projects in execution.
Monitoring the project progress against planned schedule.
Details
Task
:
To breakdown the project into distinct activities which includes the
time
estimation for the activities and sequence of the works.
Establish
project schedules and monitor against productivity.
Feedback
the updates schedule to Project Manager and management.
To
formulise an effective tactical decision making based on strategy.
Establish
resources list of manpower, equipment, tools and
consumables.
Establish
manpower, equipment loading based on the tender schedule.
To
establish and evaluation of project in term of resources, i.e
manpower,
tools, consumables and etc.
Responsibility
:
To co-ordinate in logical order all the activities, person, machines and
Materials necessary to complete a project.
Prepare,
updating project schedule on daily, weekly and monthly report.
Confirmation
with other parties that may have involvement on
tendering process.
Project
Tendering &
Negotiation
Involved
:
1. The 3 X 700 MW Coal Fired Power Station Project Manjung Perak for TNB Janamanjung Sdn. Bhd
2.
TNB Gelugor Pulau Pinang Power Station Upgrading Project.
3.
Sepang Power Station – Simmens Open Cycle Stage
Involved
on direct high level negotiation with sub-contractor and ABB Power Generation
Sdn. Bhd. on
final
claiming matter for the Titan Petrochemical projects as part of close up project
procedure.
PROMTO-SIKOJAYA
SDN. BHD.
Duration
Position
:
1st Jan 1999 until 31st Jan 2000
Position
:
Acting Site Manager
Project
Involved
:
Titan Petrochemical Combined Cycle Power Plant
Client
:
ABB Power Generation Sdn. Bhd. (Now As Alstom
Power
Malaysia
Sdn. Bhd.)
Installation and pre-commissioning of ABB Combined Cycle Power Plant for
Titan Petrochemical plant at Tanjung Langsat, Johor Bahru.
a)
1 unit ABB (GT-21) Gas Turbine including all its associated auxiliary
equipment, piping, electrical & instrumentation.
b)
1 unit ABB Heat Recovery System Generation (HRSG) including structural
erection, auxiliary equipment, piping, electrical & instrumentation.
c)
1 unit ABB MP Steam Turbine including all its auxiliary equipment,
piping, electrical & instrument system.
Mechanical
and Structural Installation & Pre-commissioning: -
Ø
Boiler Modules
(Superheater, Evaporator and Economiser)
Ø
Boiler Feed
Pumps
Ø
Boiler
Circulation Pumps
Ø
Gas Turbine
Ø
Auxiliary
equipment & piping systems, valves and fittings
Electrical
& Instrument Installation and Pre-commissioning: -
Ø
Transformers
Ø
Main Switch
Board / Switchgears
Ø
Electrical
Feeders
Ø
Electrical
Distribution Panels
Ø
Instrumentation
Control Panels
Ø
Instrumentation
Field Instrument
Ø
E & I
Auxiliary accessories such as cable trays/ladders, power cables, instrument
cables, support, etc.
Duties
and responsibilities: -
Ø
Ensure every
required resource such as tools, equipment, project materials; technical
drawings, other relevant referential documents, external technical supports and
general site administrative support are in place and being closely monitored.
Ø
Ensure the
plant is constructed in accordance with client and main contractor requirements.
Ø
Site management
and co-ordination with sub-contractor.
Ø
Management and
co-ordination of resources to ensure the programme of work is achieved.
Ø
Adherence to
the Safety Policy and requirements per Occupational Health and Safety Management
Plan.
Ø
Employee
relation plan.
Ø
Quality
requirements for site works.
Ø
Identify and
record any non-conformity relating to the job.
Ø
Represent
company in day-to-day interfaces with client, main contractor and sub-contractor
on reporting.
Ø
Advising
Project Manager or Procurement Manager of shortfalls in supply of plant or
equipment to site.
Ø
Authorise to
purchase material from site.
Ø
Authorise
sub-contractor to precede work on variation order.
Ø
Authorise to
control further processing or installation of non-confirming product until the
deficiency or unsatisfactory condition has been corrected.
Ø
Controlling
project budget.
PROMTO-SIKOJAYA
SDN. BHD.
Duration
Position
:
22nd June 1998 until 31st December 1998
Position
:
Site Engineer
Project
Involved
:
Titan Petrochemical Cogen 2 X 40MW Power Plant
Client
:
ABB Power Generation Sdn. Bhd. (Now As Alstom Power
Malaysia
Sdn. Bhd.)
Installation and pre-commissioning of ABB Co-Gen Power Plant for Titan
Petrochemical Sdn. Bhd at Pasir Gudang Johor.
a)
2 units ABB GT-10 Gas Turbine including all its associated auxiliary
equipment, piping systems and electrical cabling works.
b)
2 units of ABB Heat Recovery System Generation (HRSG) including
structural erection, auxiliary equipment, piping, electrical & instrument
systems.
Mechanical and Structural Installation & Pre-commissioning: -
Ø
Boiler Modules
( Superheater, Evaporator and Economiser )
Ø
Boiler Feed
Pumps
Ø
Boiler
Circulation Pumps
Ø
Gas Turbine
Ø
Auxiliary
equipment & piping systems, valves and fittings
Electrical & Instrument Installation and Pre-commissioning: -
Ø
Transformers
Ø
Main Switch
Board / Switchgears
Ø
Electrical
Feeders
Ø
Electrical
Distribution Panels
Ø
Instrumentation
Control Panels
Ø
Instrumentation
Field Instrument
Ø
E & I
Auxiliary accessories such as cable trays/ladders, power cables, instrument
cables, support, etc.
EQUATOR
ENGINEERING SDN. BHD.
Duration
of Employment
:
Sept 1996 - June 1998
Position
:
Mechanical Engineer
Project
Involved
:
TNB SSAA Power Station Phase III 2 X 500MW Turbine Contract.
Client
:
TBV Power (M) Sdn. Bhd.
a)
2 units of GE
Steam Turbine including all its associated auxiliary equipment, piping systems.
b)
Mechanical
equipment for Electrochloronation Plant.
c)
Piping for
balance of plants systems.
d)
2 units of
Condenser.
e)
Mechanical
equipment for Balance of plants systems.
f)
Mechanical
equipment for CW Pump house.
g)
Mechanical
equipment and piping for Demin Plant.
Duties
& responsibilities: -
Ø
In-charge in
preparing, updating project timetable on daily, weekly and monthly progress
report.
Ø
Updating actual
activities which to be compared with planned activities using Primavera Project
Planner.
Ø
Monitoring and
supervising mechanical erection, piping and welding activities.
Ø
All project
technical and administrative documentation are properly filed to ensure smooth
closing up upon project completion.
Ø
Ensure all
safety procedures are complied in all critical works execution such as heavy
lifting, scaffolding, confined space entry and so on.
Ø
Issue purchase
order to purchase material from site.
Ø
Co-ordinate
with other parties that may have some involvement on the project.
Ø
Supervising one
piping section consist of 12 semi skilled pipe fitters, 12 skilled pipe fitters
and one foreman.
CMKS(M)
SDN. BHD.
Duration
of Employment
:
July 1993 until Sept 1994
Position
:
Technician
Duties
& responsibilities:
Ø
Maintenance of
mould punching and drilling machines.
Ø
Modification of
mould as per new design.
Ø
Repairing mould
in order to support production line.
Ø
Operates of
various machinery’s as milling, grinding and wire cut.
Ø
Incharge of
incoming & outgoing goods.
Ø
Supervise 10
operators.
1.
Prof. J. Rhodes
(Project Supervisor)
Department of Mechanical Engineering
University of Strathclyde Glasgow U.K
2.
Madam Rokiah
Mohamad Noor (Assistance Manager)
CMKS (M) Sdn. Bhd.
Pasir Gudang Industrial Estate
Johor.
3.
Osman Bin Asri
(Assistance Manager)
EQUATOR Engineering Sdn. Bhd.
Shah Alam Selangor.
4.
Lim Yew Hock
(Assistant Purchasing Officer)
Promto-Sikojaya Sdn. Bhd.
Lot 10, Jalan U1/15, Seksyen U1
Hicom Glenmarie Industrial Park.
40150 Shah Alam Selangor.
5.
Malik Bin
Sulaiman (PMSI)
ALSTOM POWER Sdn. Bhd. (Company No. 243308H)
21st Floor, Wisma Genting,
28, Jalan Sultan Ismail,
50250 Kuala Lumpur.
6.
Keneeth Ngui (PMSI)
ALSTOM POWER Sdn. Bhd. (Company No. 243308H)
21st Floor, Wisma Genting,
28, Jalan Sultan Ismail,
50250 Kuala Lumpur.
7.
Riduan Bin
Buyong
37th Floor Menara PNB
201A Jalan Tun Razak,
50450 Kuala Lumpur.
8.
Daniel Wong Bin
Abdullah
Petronas Penapisan Melaka Sdn. Bhd.
Persiaran Penapisan
76300 Sungai Udang
Melaka.
9.
Mohd. Bakhit
Bin Mohd. Nor
Petronas Gas Berhad.
KM 8, Kg Tok Arun Off Jalan Santong,
23100 Paka, Dungun,
Terengganu.
10.
Zubir Bin Abdul
Razak
Petronas Dagangan Berhad
Level 33, Tower 1, Petronas Twin Towers,
Kuala Lumpur City Centre,
50088 Kuala Lumpur.